Gravity Retaining Wall Installation

Gravity Retaining Wall Installation
Below is a step by step Gravity Retaining Wall Installation process. This is to be used as a guide and instruction manual of the proper procedures needed to install a MagnumStone project correctly and efficiently. All information provided is to be used at the discretion of the user.

Call before you dig. These are typically free services in most counties and jurisdictions. They will come to the site and mark out where all of the utilities are underground. 

Canada – digsafe.ca

USA – call811.com

Australia – byda.com.au

United Kingdom – national-one-call.co.uk

New Zealand – beforeudig.co.nz

STEP
01

Planning The Gravity Retaining Wall

Review

  • Mark the bottom and top of the gravity retaining wall excavation location with spray paint or stakes

  • Establish proper elevation points for both the bottom and top of the wall before starting excavation

  • Organic Materials should not be used in any Backfill Zones

  • Store and protect good quality Backfill Materials from inclement weather during construction

STEP
02

Excavating The Geogrid Retaining Wall

Figure 1

Review

  • Excavate and prepare Sub Base Levelling Trench 6 to 8″ (150 to 200mm) below first course. This will be filled with a good 3/4″ (20mm) road base material.

  • Figure 1 – The Leveling Pad Trench Depth should be cut out to approximately 6″ (15cm) from the back and and the front of the total depth of the base course. For instance, MagnumStone Standard Unit 24″ + 6″(front) + 6″(back) = 36″ total (610 mm + 150 mm + 150 mm = 910 mm)

  • Typical retaining wall burial depth or embedment Depth is 6″ to 12″ (150 to 300mm). Follow engineers cross section details or design parameters to ensure the correct embedment depth is being followed.

  • Excavate cut line to a 2 to 1 slope or greater. Check with local codes and regulations to ensure they are being followed correctly.

STEP
03

Sub Base and Base Stabilization Fabrics

Review

  • Compact Sub Base to 95% Standard Proctor Density or greater

  • Remove any Organic or poor soils in the Sub Base and replace with proper reinforced fill materials before compacting

  • (Optional) place 5′ to 6′ (127 to 152mm) wide Base Stabilization Fabric on top of leveling pad trench

  • Base Stabilization Fabrics will help prevent sub base materials from mixing with the gravel base leveling pad during compaction

  • Fabric also provides extra Structural Bearing Stability to the base leveling pad

STEP
04

Compact Gravel Leveling Pad

Review

  • Typically a 3/4″ (20mm) road crush gravel or equivalent is used for the base leveling pad

  • Compact Gravel Leveling Pad to 95% Standard Proctor Density or greater

  • Correct Moisture Content in the gravel will help in reaching proper compaction

  • It is crucial that the base is level front to back and side to side. Any imperfections will be exaggerated as the wall goes taller

STEP
05

Laying First Course of the Gravity Retaining Wall

Review

  • Remove the Screed Pipes from the leveling pad

  • Place a steel stake at either end of the leveling pad to establish the back of the first course of units

  • Secure tightly a string line to the stakes at either end which will provide the guide to line up the back of each MagnumStone™ base unit

  • The distance of the string line between the steel stakes may vary due to heavy winds

  • MagnumStone™ base units, placed on the leveling pad, are manufactured without SecureLugs

  • Place each unit on top of the leveling pad in such a way as not to disturb the level gravel

STEP
06

Installing Extender Units to MagnumStone™ Block

Review

  • Place the tongue of the extender block inside the groove of the MagnumStone Base Block If extender to extender blocks are required place them in the same manner as the previous ensuring that the blocks stay level and true.

STEP
07

Complete Base Row Installation

Review

  • Place the next MagnumStone Retaining Wall blocks level and aligned front to back and side to side

  • Install the MagnumStone base block on the leveling pad. The base block should not have the lugs on the bottom. Ensure that the blocks are level front to back and side to side.

  • Complete the first course of the gravity retaining and all extender units that are in the design.

STEP
08

Drain Pipe Options and Uses for Gravity Retaining Wall

Review

  • Option #1

  • A fabric wrapped or Perforated Drain Pipe should have adequate slope to drain water in the right direction towards each Drain Pipe Outlet

  • Drain Pipe Outlet can be every 30 or 50 feet (9 or 15 meters)

  • Perforated Drain Pipe, laid in the Horizontal Cores, can be a Sock Wrapped system to help prevent fines from migrating into the pipe

  • Option #2

  • A fabric wrapped or perforated drain pipe may also be placed at the back of the of the retaining wall blocks near the excavation cut line

STEP
09

Backfill the Gravity Retaining Wall

Review

  • Backfill the MagnumStone blocks and extender units with a clear crush gravel (#57 Stone) or equivalent slightly above the units. Run a plate vibratory compactor over the stones and units allowing them to settle in the hollow cores. Sweep any excess stones off the top of the units and blocks.

STEP
10

Installing Soil Separation Fabrics

Review

  • Install a soil separating fabric (Filter Fabrics) to separate the fines and compacted backfill material from the drainage aggregate. The filter fabric can be installed directly behind the MagnumStone extender units. They can also be installed directly on top of the drainage gravels.

STEP
11

Installing Next MagnumStone Row of Retaining Wall Blocks

Review

  • Lay the Next row on a running Bond pattern with the SecureLugs Connected in the hollow core below. The SecureLug Connection provides a strong block to block connection and alignment throughout building your retaining wall.

STEP
12

Continue Installation of Retaining Wall Blocks

Review

  • Continue to place the MagnumStone blocks on top of the retaining wall blocks below. Ensure they are level front to back ans side to side. Small adjustments may need to be made during the construction process. Soil separation fabrics can be added wherever the backfill meets the drainage gravel to keep fines from migrating into the drainage zone.

STEP
13

Backfill and Compact Approved

Review

  • Compact the approved backfill materials in between the excavation cut zone and the back of the retaining wall blocks. Ensure that it compacted in lifts of no more that 8″ (203mm) and also compacted to 95% standard proctor density. It is crucial that these areas do not have loose fill where settlement can occur.

STEP
14

Continue Installation of MagnumStone Big Block Gravity Retaining Wall

Review

  • Continue the installation of MagnumStone big block gravity retaining wall as per the design provided. Cross section drawings will show you where the units are placed in order of depth.

STEP
15

Continue Installation of MagnumStone Big Block Gravity Retaining Wall

Review

  • Continue the installation of MagnumStone big block gravity retaining wall as per the design provided. Cross section drawings will show you where the units are placed in order of depth.

STEP
16

Top Block of Gravity Retaining Wall

Review

  • Install the top MagnumStone retaining wall block like the rest of the wall. The top block will not have the back edge on the top. This is the location that the soil separation fabric will lay to protect the hollow core and drainage channel of the block.

STEP
17

Finish Your Gravity Retaining Wall

Review

  • Grade the final elevations of your gravity retaining wall.